Monday, 13 July 2009
Contract Manager's Update
- We are now 50% completed on the external drainage
- Decoration – 30% completed
- Commenced 2nd fix M&E and Joinery, approx 30% completed
- Windows and Doors – 80% completed
- Sedum roof - 60% completed
- Plastering – completed, except the refurb to school, which is due to commence during the summer hols
ADMINISTRATION BLOCK
- Roof structure – completed
- Screed – completed
- Windows and Doors – 80% completed
- 1st fix all trades – 70% completed
Labels:
progress