We're at decoration and third fix stage on this project, and external works are around 85% complete. The main contract is due to be completed in November as planned, but there is a possibility of follow on works that could run into February or March of 2010. We'll keep you posted here. Current subcontractors on site are all performing excellently. These include Linx Electrical, HF Brown (Mechanical), K M Davies (Flooring) and HD Decorators
Bernard Porter