A meeting was held on site between myself Jed Holden and Tony Noble from East Riding Council to determine the soffitt details for all of the lower roofs. I pointed out that the current detail involved a huge amount of work which would result in a fairly poor end product. I suggested that we underdraw all the soffitts. Jed confirmed that this was accecptable and that once this was complete it may be required to fix false spars on the underside of the sofftit to create the desired appearance.
Portakabin atended site to collect the temporary classrooms from the Junior school site, everything went well and there where no reported problems.
Work in Progress - Cedar board cladding, 1st fix all trades, demolition of existing junior school, floor insulation to ground floor.
The information above forms part of a daily diary that I now complete on H&P Collaborate, our new web based extranet. This new system means all H&P staff can stay bang up to date with progress on our sites.