Monday, 13 July 2009

Contract Manager's Update

MAIN BUILDING
  • We are now 50% completed on the external drainage
  • Decoration – 30% completed
  • Commenced 2nd fix M&E and Joinery, approx 30% completed
  • Windows and Doors – 80% completed
  • Sedum roof - 60% completed
  • Plastering – completed, except the refurb to school, which is due to commence during the summer hols
ADMINISTRATION BLOCK
  • Roof structure – completed
  • Screed – completed
  • Windows and Doors – 80% completed
  • 1st fix all trades – 70% completed
We are due to commence the refurbishment to the school on Monday 20th July 2009 (summer hols) and also the works to the new Kitchen.

Friday, 26 June 2009

Site manager's progress report


We are currently doing the external rendering, using George Howe who are doing a good job. JFS are installing all the doors and windows, and Martin Humble is plastering internally. Elsewhwere Healy and Linx are continuing the meachanical and electrical. We've worked with these forms before and they are all doing their usual professional job. The contract is due to complete at the end of November and is currently ahead of programme.